Take a look at a range of scaffolding projects completed for homeowners, contractors and developers across the UK, from domestic home extensions and roofing works to housing developments, commercial sites and specialist access installations. Every project is carefully planned around safe access, efficient installation and the practical demands of the service being carried out.
New Build
Existing
SM Lucks Lane Development
- King's Lynn
- 16 weeks
Brief
Scaffolding installed for a large new build housing development in King’s Lynn, providing safe access across multiple active construction phases.
Challenges
The development required carefully phased scaffolding installation around ongoing construction activity, restricted site access and tight delivery schedules.
Our Solution
Our scaffolding partners installed secure perimeter access, loading bays and phased scaffold systems designed to support contractors safely while keeping the wider development programme moving efficiently.
Outcome
The project was completed safely and on schedule, helping maintain construction progress across the wider residential development with minimal disruption on site.
New Build
New Build
Bloor Homes
- Swavesey
- 8 weeks
Brief
Scaffold erected around active timber frame plots at a Bloor Homes development in Swavesey to support first-fix roofing and upper-level construction works.
Challenges
Multiple plots were being built simultaneously, requiring flexible scaffold adaptations as roof structures, access points and working areas changed week by week.
Our Solution
Custom scaffold lifts and boarded access routes were installed to allow roofers and site trades to move safely between working levels during rapid build progression.
Outcome
The scaffold setup allowed trades to continue working efficiently across several plots at once, helping maintain momentum during key stages of the development.
Domestic
Existing
McCarthy & Stone – Cloud Nine
- Felixstowe
- 12 weeks
Brief
Specialist scaffold access installed around upper-level exterior works at the Cloud Nine development, allowing contractors to work safely at height during final build stages.
Challenges
Strong coastal winds, restricted ground space and constant movement of plant equipment created a demanding environment for scaffold planning and daily site access.
Our Solution
Cantilevered scaffold sections and reinforced boarded lifts were used to create stable elevated access around exposed working areas without interrupting surrounding site activity.
Outcome
The scaffold installation allowed external finishing works to continue safely through changing site conditions, helping keep later-stage development works on track.
Commercial
New Build
McCarthy & Stone – Cranberry Court
- Cambridgeshire
- 14 weeks
Brief
External scaffold access installed around Cranberry Court to allow façade trades, roofing contractors and finishing teams to continue works safely on elevated sections of the development.
Challenges
The corner-site layout created limited working space around pedestrian routes, delivery vehicles and neighbouring access roads during scaffold assembly.
Our Solution
A wrapped scaffold configuration with protected pavement access and staggered working lifts was designed to maximise usable workspace around the building perimeter.
Outcome
The scaffold arrangement allowed multiple exterior trades to operate simultaneously while maintaining safe access around the active development frontage.
Commercial
Existing
McCarthy and Stone – Retirement Property
- Market Harborough
- 10 weeks
Brief
Temporary scaffold access and edge protection systems installed around a retirement living development to support masonry, roofing and upper-floor construction works.
Challenges
The narrow footprint of the site meant scaffold materials, waste removal and contractor access all had to be managed within tightly controlled working zones.
Our Solution
A staged scaffold erection programme was used to open up different sections of the building progressively as brickwork and roof structures advanced.
Outcome
The access setup enabled trades to continue working across multiple elevations simultaneously while maintaining organised movement throughout the live construction site.
Domestic
Existing
Residential Apartment Maintenance Scaffold
- Cambridgeshire
- 3 weeks
Brief
Scaffold access installed around an occupied residential apartment building to support balcony maintenance, roofing repairs and exterior inspection works.
Challenges
The project required careful scaffold positioning around landscaped grounds, resident entrances and elevated balcony areas without restricting day-to-day access.
Our Solution
A lightweight independent scaffold system was erected around the upper elevations of the building, allowing contractors to carry out repairs safely while residents remained on site.
Outcome
The maintenance works were completed with minimal disruption to residents, providing safe elevated access across difficult-to-reach sections of the property.